Foundation & Footing
Excavation, bearing, rebar cover & continuous pour for stable foundations.
Scope Overview
Strong, precisely constructed foundations and footings that provide a stable, lasting base for your structure — including continuous footings, spread footings, and stem walls set to design elevations.
Technical Specification
Specification Details
01
Material & Mix Specification
| Parameter | Specification |
|---|---|
| Concrete Mix | Ready-mix, 3,000–4,000 psi @ 28 days (per structural design) |
| Slump | 4 in ± 1 in |
| Reinforcement | #4 or #5 rebar per structural drawings (bent & tied) |
| Coarse Aggregate | 3/4 in max |
| Embedment | Per geotechnical & frost-depth requirements |
02
Execution & Tolerances
| Parameter | Specification |
|---|---|
| Excavation | To design depth & width; bench & dewater as required |
| Bearing | Undisturbed soil or compacted fill at design bearing capacity |
| Rebar | Placed on chairs; minimum 3 in cover (against earth) |
| Forms | Plumb, braced, set to finish elevation |
| Placement | Continuous pour; vibration to consolidate |
| Curing | 7 days; protected from premature drying & freeze |
03
Quality Assurance & Acceptance
- Excavation and bearing surface verified against geotechnical recommendations.
- Reinforcement size, spacing, lap, and cover confirmed prior to pour.
- Concrete-strength test cylinders cast and lab-tested per project requirements.
- Inspection sign-off obtained before proceeding with the superstructure.
Need this spec tailored to your project?
These sheets are our standard baseline. For project-specific specifications and a detailed estimate, send us your project details.